KMHI's New Home

Menu:
Interior progress    9/24
Finish work   10/13
Progress log    6/14
Building set   6/14
Excavation       6/14
Site plan         10/12
Elevations    10/12 (PDF)
Floor plan    10/12 (PDF)
KMHI Web Site

    
Progress Log
9/24/07 - We're enjoying the new office space and meeting facilities.
6/14/07 - Everything came together and the office was set.
6/5/07 - Masonry is complete and the target house arrival is June 12.
5/31/07 - Masonry.
5/21/07 - The footers are poured.
5/17/07 - Foundation work is underway with concrete pouring planned
4/19/07 - After complications with the easements, all easements are filed and the next phase of construction is ready to continue.
4/15/07 - The Classroom in the new KMHI modular office building will be named "Bill Poynter Education Wing" to include an appropriate display listing Mr. Poynter's major contributions to the industry and to KMHI.
2/7/07 - Construction Timeline:
  1. Release of easements - Last week of February or first week of March
  2. Complete foundation for delivery of building - Two weeks (weather permitting)
  3. Site visit and delivery of building  - 1 week
  4. Installation, site work and trim out of building by Patriot - Two weeks (weather permitting)
  5. Parking lot, sidewalks, post installation site work - One month (weather permitting)
  6. Possible move-in date - Mid-May

1/8 - Interior progress & pictures. Thanks Craig Curtis @  Energy Mate. more ...
1/4 - The weather has been cooperating to allow excavation.
11/28 - Trenching
11/6 - Pictures of the excavation. click
10/26 - Site demolition and preparations are underway.

As of 9/25:

  1. Site plan, water and sewer, storm water run-off, drainage plan approved by Franklin County Planning and Zoning.
  2. Foundation/footer layout provided by EnergyMate
  3. Architectural design and floor plan completed.
  • The old building is gone and the new modular office building is ordered.
  • The EnergyMate Homes Division of Patriot Homes, Inc in Elkhart Indiana will be building our structure.
  • This new building will better serve the KMHI and will present a more attractive, professional and credible image to the public.
  • The building will be one story, approximately 4,100 square feet.
  • We will have a reception area, offices, storage, a kitchen and restrooms. Separate men’s and women’s restrooms!
  • An important addition are the new classrooms.

 